What matters most
- Agree the cosmetic limits and the gauging method before the first shot.
- Record voids, lines and polarized-light stress by location.
- Check against mating parts and sealing faces, not only dimensions.
Make every trial end in a decision
Evaluate the technical choice together with part requirements, tooling consequences, production controls, and the evidence required for approval.
Standard
Agree the cosmetic limits and the gauging method before the first shot.
Clarity and stress
Record voids, lines and polarized-light stress by location.
Fit
Check against mating parts and sealing faces, not only dimensions.
Corrections
Log each change with an owner and a due date.
Technical guide
The sections below retain the detailed design, tooling, process, and quality context needed to evaluate this topic beyond the summary.
A lamp mold trial is easy to waste. Without a shared checklist, each person looks at something different and the next trial repeats the same arguments. This guide gives a practical list for T0 and T1 on lens, reflector and housing parts. For the overall staging, read the T0 to T3 trial stages guide.
Agree the standard before the trial
- Cosmetic defect standard for each surface class, with sample photos or limit samples.
- Dimensional characteristics and which gauges or fixtures will be used.
- Resin lot, drying record and process sheet to be used.
- Who decides pass, conditional pass or fail, and how it is recorded.
T0: does the tool work?
- Fills completely and consistently without short shots or burns.
- Releases without sticking, dragging or deformation.
- Parting line, shutoffs and any slides or lifters operate without damage or flash.
- Fit with the mating parts, checked on a sample set before any tuning.
- First map of defects and their locations for the correction list.
T1: is it converging?
| Check | What to record |
|---|---|
| Clarity and surface | Voids, sink, flow and weld lines, gate vestige, scuffs; location and photograph each |
| Molded-in stress | Polarized-light result and agreed acceptance for each area |
| Dimensions | Critical dimensions and flatness or warpage against the drawing, with the measurement method |
| Fit and function | Assembly with the lens, housing or bezel, and any gap or sealing-face issue |
| Process window | Settings used, and how sensitive the part is to small changes |
| Corrections | Each mold or process change, owner and due date |
Close each trial with a decision
End every trial with one of three outcomes: accepted, accepted with listed corrections, or repeat with a changed plan. Keep the sample set and the report together so the next trial starts from evidence, not memory. For capability evidence at part approval, see first article inspection.
Roles and communication
Name who attends the trial from the buyer, the molder and the tool maker, and who has authority to approve a mold change on the spot. Agree how results are shared afterward, ideally the same day, with photographs and a numbered list. A short, shared summary with owners and dates keeps the schedule honest and prevents the same issue being rediscovered at the next trial. If the trial is remote, agree in advance which images, measurements and videos you need to see to make a decision.
Evidence to bring to the trial
- The released drawing revision and the model used to cut the tool.
- The material certificate and drying record for the resin lot.
- A process sheet showing the planned settings, so changes can be logged against it.
- The measuring plan: which dimensions, with which gauge or fixture, on how many parts.
Common T0/T1 findings on lamp parts
Clear parts show their problems early. Typical findings are voids in thick sections, sink on the appearance side of ribs, flow lines near the gate, a burn at the last-filled corner, drag marks on poorly drafted faces, flash at a shutoff, and warpage that moves the sealing face. Each has a most likely cause in gate, cooling, venting, draft or packing, which is why logging the location and photograph matters more than the label. A finding without a location cannot be traced to a mold change.
Moving from T1 to approval
When the corrections from T1 are made, the next trial should be shorter and more focused on capability: a stable process window, a repeatable sample set, and measurements that match the drawing. Part approval for an automotive program is usually governed by the customer's PPAP rules, which are covered in the PPAP and APQP guide. Keep the trial reports so the approval package can reuse the evidence.
What to confirm before supplier review
Use the drawing, material specification, expected demand, application conditions, and acceptance requirements to turn a general process discussion into a program-specific review.
- What cosmetic standard and limit samples apply?
- How will stress be checked on clear parts?
- Which dimensions and fits decide acceptance?
- Who signs off, and how are corrections tracked?
Continue the engineering review
Use the related guides and capability pages to connect this topic to part geometry, tooling, molding, and qualification decisions.